GABLE/DORMER
INSULATION & SIDING INSTALLATION
Install 1/2-inch insulation board to the
exterior sides of stud walls in the gables and dormers using plastic-top
cap nails or shingle nails. Log
siding is to be installed on the exterior side of the insulation board.
Be certain that flashing is properly installed where dormer stud
walls join the house roof to prevent leaking.
Cut the siding ends according to the roof pitches joining the
siding. Be sure to use
galvanized nails to prevent rust streaking.
Caulking may be used to seal cracks where siding joins the roof
overhangs. |
|
CLICK HERE to learn more and/or register, and read hundreds of testimonials.
FREE Literature
FREE Monthly Newsletter
Home Shows
Quality Links
|
click the partial testimonial below to read more from this satisfied customer
|
| Questions? Click Here to e-mail Pati Site Map Please read our Privacy Statement Legal Notice | ||
| The Natural Choice For Over 32 Years © 1995-2007 Tennessee Log Homes, Inc. | ||
| CALL us: 1.800.251.9218 FAX us: 1.423.744.8156 E-MAIL us: CLICK HERE | ||
|
VISIT us: I-75, Exit 49, Halfway between Chattanooga & Knoxville, TN, across from Applebee's |
||